Question 46

Multiple Choice

Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1) to be processed, as shown in the following table. Assume the shop works eight hours per day.
Table J.11 Work center Q45 has four jobs that just arrived (the start of Day 1)  to be processed, as shown in the following table. Assume the shop works eight hours per day.    -Using the information in Table J.11 and the shortest processing time (SPT)  rule, what should be the sequence of jobs processed at Q45? A)  C-D-A-B B)  D-A-C-B C)  A-D-B-C D)  B-A-D-C
-Using the information in Table J.11 and the shortest processing time (SPT) rule, what should be the sequence of jobs processed at Q45?


A) C-D-A-B
B) D-A-C-B
C) A-D-B-C
D) B-A-D-C