Multiple Choice
Table J.15
Consider the following problem in which four jobs that arrived this morning are to be processed on two machines. They start with the cutting machine and then go to the painting machine. The following processing times are available (in hours) :
-Use the information in Table J.15. If the SPT rule is used to determine the sequence at the cutting machine and the same sequence is also used at the painting machine, what is the makespan through both machines?
A) fewer than or equal to 32 hours
B) greater than 32 hours but fewer than or equal to 34 hours
C) greater than 34 hours but fewer than or equal to 36 hours
D) greater than 36 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q44: Table J.5<br>The following three jobs just arrived
Q45: Table J.11<br>Work center Q45 has four jobs
Q46: Table J.11<br>Work center Q45 has four jobs
Q47: Table J.1<br>The framing department has six jobs
Q48: Table J.8<br>Auto Data produces custom engineering testing
Q50: _ is a priority sequencing rule that
Q51: A job shop is accompanied by divergent
Q52: Table J.11<br>Work center Q45 has four jobs
Q53: Johnson's rule is a procedure that minimizes
Q54: A(n) _ specializes in medium- to high-volume