Multiple Choice
Table J.17
A company must take on seven new projects. Each project has a planning stage and a design stage, and the planning stage must be completed before the design stage can begin. Also, two project teams are available to work on these projects: Team 1 works only on planning stages of projects, and Team 2 works only on design stages of projects. The times to complete the project stage, in days, are shown in the following table.
-Using the information in Table J.17 and Johnson's rule, how much idle time does Team 2 have from the start of the first project through completion of the seventh?
A) 2 days
B) 3 days
C) 4 days
D) 5 days
Correct Answer:

Verified
Correct Answer:
Verified
Q97: Table J.11<br>Work center Q45 has four jobs
Q98: Table J.8<br>Auto Data produces custom engineering testing
Q99: When using the critical ratio (CR) priority
Q100: Consider this list of jobs that have
Q101: The sum of scheduled receipts for all
Q103: Table J.16<br>Five jobs are currently waiting to
Q104: _ is the total amount of time
Q105: Table J.2<br>Stu Dent reviews the syllabi he
Q106: Table J.12 The Feast<br>Janice prepares a medley
Q107: Acme has an overabundance of machinery available,