Multiple Choice
When using the critical ratio (CR) priority sequencing rule:
A) a ratio of less than 1.0 implies that the job is ahead of schedule.
B) a ratio of less than 1.0 implies the job is behind schedule.
C) the job with the earliest due date is scheduled next.
D) the job with the highest CR is scheduled next.
Correct Answer:

Verified
Correct Answer:
Verified