Multiple Choice
Five samples of size 4 were taken from a process. A range chart was developed that had LCLR = 0 and UCLR = 2.50. Similarly, an average chart was developed with the average range from the five samples, with LCL = 15.0 and LCL = 24.0. The ranges for each of the five samples were 1.75, 2.42, 2.75, 2.04, and 2.80, respectively. The values of the sample average for each sample were 19.5, 22.3, 17.4, 20.1, and 18.9, respectively. What can you tell management from this analysis?
A) The process variability is out of control, and we cannot make a statement about the process average.
B) The process variability is out of control, but the process average is in control.
C) The process variability and the process average are out of control.
D) We cannot tell if the process variability or the process average is out of control.
Correct Answer:

Verified
Correct Answer:
Verified
Q45: Four samples of 100 each were taken
Q46: What are the steps in the Six
Q47: Continuous improvement is one of the four
Q48: Regarding control charts, changing from two-sigma limits
Q49: The TQM pillar of _ involves the
Q51: The notion of internal customers applies to
Q52: _ are small groups of supervisors and
Q53: What are any three dimensions of quality
Q54: The internal failure known as _ occurs
Q55: Describe the systems approach for total quality