A standard work year is 2,080 hours at the Luther Mill and it takes about 2 hours to fill a customer order. The manager at the mill is always concerned about employee idle time, so he aims for a capacity cushion of two percent. Last year saw 15,000 customer orders at the mill and the manager has a new Mercedes in mind as a company car, so he hopes that there is an increase of 10% in customer orders for next year. How many workers will the manager need to have at the mill next year?


A) 10
B) 13
C) 16
D) 19