Multiple Choice
Use the process flow diagram to determine which of these events has the greatest net benefit.
A) reducing the flow time at Station A from 8 to 7 minutes
B) increasing the capacity at Station B to 8 units per hour
C) increasing the capacity at Station C to 7 units per hour
D) reducing the flow time at Station D from 9 to 8 minutes
Correct Answer:

Verified
Correct Answer:
Verified