Multiple Choice
The fourth step in Theory of Constraints application, "elevate the bottleneck(s) ," means that the analyst should:
A) create a schedule that maximizes the throughput of the bottlenecks.
B) repeat the analysis process to look for other bottlenecks.
C) consider increasing capacity of the bottleneck.
D) schedule non-bottleneck resources to support the bottleneck.
Correct Answer:

Verified