Multiple Choice
Table 5.1
A company makes four products that have the following characteristics: Product A sells for $50 but needs $10 of materials and $15 of labor to produce; Product B sells for $75 but needs $30 of materials and $15 of labor to produce; Product C sells for $100 but needs $50 of materials and $30 of labor to produce; Product D sells for $150 but needs $75 of materials and $40 of labor to produce. The processing requirements for each product on each of the four machines are shown in the table.
Work centers W, X, Y, and Z are available for 40 hours per week and have no setup time when switching between products. Market demand for each product is 80 units per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product.
-Use the information in Table 5.1. Using the bottleneck method, in what sequence should products be scheduled for production?
A) D, C, B, A
B) D, C, A, B
C) C, D, A, B
D) C, D, B, A
Correct Answer:

Verified
Correct Answer:
Verified
Q122: The fifth step in Theory of Constraints
Q123: Describe a process from your own personal
Q124: Balance the line in order to achieve
Q125: Consider consecutive processes A-B-C, where process A
Q126: An assembly line has to perform 10
Q128: Table 5.7<br>The Terminal Company is attempting to
Q129: Table 5.5<br>Balance the following line for an
Q130: Balance the assembly line using the following
Q131: What is the definition of "theoretical maximum
Q132: Table 5.4<br>The Superior Management Company assembles muffalettas