Multiple Choice
An assembly line has to perform 10 work elements, whose time requirements follow. An operations analyst has found a solution using some heuristics, as shown in the table. If the cycle time of the line is 90 seconds, what is the efficiency of the assembly line?
A) less than 85%
B) greater than 85% but less than 90%
C) greater than 90% but less than 95%
D) greater than 95%
Correct Answer:

Verified
Correct Answer:
Verified