Multiple Choice
Regarding the Eight Types of Waste that must be eliminated to implement lean systems, using expensive high precision equipment when a simpler machine would suffice is part of which general waste category?
A) Motion
B) Overproduction
C) Inappropriate Processing
D) Defects
Correct Answer:

Verified
Correct Answer:
Verified