An Item Is Used in Process B at a Rate

Question 140

Essay

An item is used in Process B at a rate of 150 units per day. Process A works one shift per day (480 minutes) and supplies Process B's requirements. What takt time is required in Process A to meet Process B's demand?

Correct Answer:

verifed

Verified

480 minutes per day ...