Essay
An item is used in Process B at a rate of 150 units per day. Process A works one shift per day (480 minutes) and supplies Process B's requirements. What takt time is required in Process A to meet Process B's demand?
Correct Answer:

Verified
480 minutes per day ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge