Case 6.1
The Edward James Toy Company uses a Kanban system to make plastic wheels that are a component of several toys. The waiting time for a container of the wheels during production is 0.25 day; average processing time is 0.15 day per container. Each container holds 200 wheels. The company uses 2,000 wheels a day in the production of its products.
-Use the information in Case 6.1. How many Kanban containers would be required if a 10% policy variable is used?
A) three or fewer
B) four or five
C) five or six
D) seven or more
Correct Answer:

Verified
Correct Answer:
Verified
Q35: Preventive maintenance is typically given very low
Q36: Takt time is the cycle time needed
Q37: In manufacturing systems, one way to achieve
Q38: To complete the current state drawing of
Q39: Long production runs, poor material flows, and
Q41: Lean systems do not need stable master
Q42: Value stream maps consist of a(n)_, a(n)_,
Q43: The final assembly schedule in a lean
Q44: An operator standing idly by his workstation
Q45: Weeding out unnecessary items, neatly arranging what's