Champion Cooling Company Uses a Kanban System at Their Location

Question 90

Essay

Champion Cooling Company uses a kanban system at their location in the Oklahoma City Metroplex. The daily demand for fans is 2,000 and management insists on using an alpha level of 0.1. They use containers that hold 24 items and takes 0.02 of a day to process. It takes 0.08 of a day to get a container filled and for it to wait during its cycle. How many containers should they use? If they use the nearest integer value number of containers, what is the actual system alpha?

Correct Answer:

verifed

Verified

k = blured image = blured image = 9.16 → 9 containers
...