Multiple Choice
With a batch size of 300 units, what is the per unit processing time for Process C?
A) 5 minutes 12 seconds
B) 5 minutes 48 seconds
C) 6 minutes
D) 5 minutes 30 seconds
Correct Answer:

Verified
Correct Answer:
Verified