Multiple Choice
Figure 7.2
-Which one of the following conditions violates the assumptions of PERT/CPM networks?
A) Some activities can have zero variance.
B) Costs increase linearly as activity time is reduced below its normal time.
C) Two activities tied together by an arc are overlapping and can be worked on simultaneously.
D) There can be more than one critical path in a network.
Correct Answer:

Verified
Correct Answer:
Verified