menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Processes
  4. Exam
    Exam 7: Project Management
  5. Question
    If the Sum of the Variances on the Critical Path
Solved

If the Sum of the Variances on the Critical Path

Question 112

Question 112

Multiple Choice

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?


A) 50 percent
B) 95 percent
C) 100 percent
D) It cannot be determined.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q107: A project manager should stop crashing a

Q108: A project is an interrelated set of

Q109: Figure 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Figure 7.2

Q110: A project organization structure where team members

Q111: A project tracking system should collect information

Q113: Table 7.9<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.9

Q114: To obtain the latest start and latest

Q115: Draw the network corresponding to the following

Q116: Table 7.14<br>You are responsible for managing a

Q117: Projects, and the application of project management,

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines