Solved

The Following Table Contains a List of Activities, with Precedence

Question 87

Essay

The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis.
a. Determine the project cost and duration without crashing.
b. Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
c. Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
d. Create a graph that shows project expediting cost plotted as a function of the reduction in project duration.
The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. a. Determine the project cost and duration without crashing. b. Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration. c. Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration. d. Create a graph that shows project expediting cost plotted as a function of the reduction in project duration.

Correct Answer:

verifed

Verified

a. Crash costs per week are shown in the...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions