Multiple Choice
Table 7.3
-Using Table 7.3, what is the earliest expected time of completion of the whole project?
A) fewer than or equal to 21 days
B) greater than 21 but fewer than or equal to 22 days
C) greater than 22 but fewer than or equal to 23 days
D) greater than 23 days
Correct Answer:

Verified
Correct Answer:
Verified
Q85: The optimistic time is the probable time
Q86: Table 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.2
Q87: The following table contains a list of
Q88: Heidi was part of a project team
Q89: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q91: When using the beta distribution for estimating
Q92: The probability that a project will be
Q93: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q94: Table 7.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.2
Q95: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"