Table 7.2 -Using Table 7.2, If the Expected Times for Activities A

Question 94

Multiple Choice

Table 7.2
Table 7.2    -Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase? A)  fewer than or equal to 2 weeks B)  greater than 2 weeks but fewer than or equal to 4 weeks C)  greater than 4 weeks but fewer than or equal to 6 weeks D)  greater than 6 weeks
-Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?


A) fewer than or equal to 2 weeks
B) greater than 2 weeks but fewer than or equal to 4 weeks
C) greater than 4 weeks but fewer than or equal to 6 weeks
D) greater than 6 weeks