Multiple Choice
Table 7.2
-Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?
A) fewer than or equal to 2 weeks
B) greater than 2 weeks but fewer than or equal to 4 weeks
C) greater than 4 weeks but fewer than or equal to 6 weeks
D) greater than 6 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q89: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q90: Table 7.3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.3
Q91: When using the beta distribution for estimating
Q92: The probability that a project will be
Q93: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q95: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q96: You are given the following information about
Q97: Describe how time-cost tradeoffs for project activities
Q98: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4
Q99: Which of these is not one of