Multiple Choice
Table 7.13
All activity times for the project are in weeks.
-Using Table 7.13, what is the expected time of completion of the project?
A) fewer than 60 weeks
B) between 60 and 65 weeks
C) between 65 and 70 weeks
D) greater than 70 weeks
Correct Answer:

Verified
Correct Answer:
Verified