Multiple Choice
Figure to accompany Table 7.1
Table 7.1
-Using the information shown in Table 7.1, what is the latest start time for activity E?
A) 2
B) 3
C) 5
D) 8
Correct Answer:

Verified
Correct Answer:
Verified