Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete?
A) less than or equal to 20%
B) greater than 20% but less than or equal to 25%
C) greater than 25% but less than or equal to 30%
D) greater than 30%
Correct Answer:

Verified
Correct Answer:
Verified