Question 149

Multiple Choice

Table 10.10
A work center has the following six jobs waiting to be processed (all times are shown in days) :
Table 10.10 A work center has the following six jobs waiting to be processed (all times are shown in days) :    -Use the information in Table 10.10. What is the average flow time (in days)  using the FCFS rule? A)  fewer than or equal to 10 days B)  greater than 10 days but fewer than or equal to 20 days C)  greater than 20 days but fewer than or equal to 30 days D)  greater than 30 days
-Use the information in Table 10.10. What is the average flow time (in days) using the FCFS rule?


A) fewer than or equal to 10 days
B) greater than 10 days but fewer than or equal to 20 days
C) greater than 20 days but fewer than or equal to 30 days
D) greater than 30 days