    Exam 14: Short-Term Scheduling
  5. Question
    A Work Center Had Actual Input of 280 Hours and Actual
Solved

A Work Center Had Actual Input of 280 Hours and Actual

Question 68

Question 68

Multiple Choice

A work center had actual input of 280 hours and actual output of 290 hours. What is the change in backlog?


A) 10
B) -10
C) 0
D) 1.037
E) Unable to determine with the given information

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q63: What are some limitations of rule-based scheduling

Q64: Five welding jobs are waiting to be

Q65: Short-term scheduling is important to efficiency and

Q66: Using SPT priority would result in what

Q67: Alaska Airlines uses mathematical short-term scheduling techniques

Q69: A recent advance in short-term scheduling that

Q70: The assignment method provides an optimum, one-to-one

Q71: Orders are processed in the sequence in

Q72: Which critical ratio value implies that a

Q73: In services, the scheduling emphasis is usually

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines