Using SPT Priority Would Result in What Sequence for Jobs

Question 66

Question 66

Multiple Choice

Using SPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4, 6, 5, and 2 respectively?


A) ABCD
B) DCBA
C) DACB
D) DABC
E) BCAD

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q61: One of the major limitations of the

Q62: Earliest due date is a shop floor

Q63: What are some limitations of rule-based scheduling

Q64: Five welding jobs are waiting to be

Q65: Short-term scheduling is important to efficiency and

Q67: Alaska Airlines uses mathematical short-term scheduling techniques

Q68: A work center had actual input of

Q69: A recent advance in short-term scheduling that

Q70: The assignment method provides an optimum, one-to-one

Q71: Orders are processed in the sequence in

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines