Multiple Choice
A grill assembly takes 20 washers. Instead of listing these washers separately, they are grouped into a single kit for production. How is the bill of material for the washers classified?
A) phantom bill
B) component bill
C) modular bill
D) low-level bill
E) planning bill
Correct Answer:

Verified
Correct Answer:
Verified