Multiple Choice
Capacity planning in closed-loop MRP:
A) utilizes feedback about workload from each work center.
B) may make use of resource requirements profiles (load reports) .
C) may smooth work center loads with such tactics as overlapping and lot splitting.
D) does not add capacity, but rather seeks effective use of existing capacity.
E) All of these are true.