Audrey Ross, Operations Manager for BCD Technologies, Must Schedule Work

Question 43

Multiple Choice

Audrey Ross, operations manager for BCD Technologies, must schedule work for the next five days. Each unit takes 20 minutes to process. Available capacity is 8 hours per day. The production order quantities are 18, 28, 38, 16, and 20 for Monday through Friday, respectively. What should be the plan for Wednesday?


A) Move 2 units to Monday, 8 units to Thursday, and 4 units to Friday.
B) Move 8 units to Monday, 8 units to Thursday.
C) Move 4 units to Tuesday, and 10 units to Thursday.
D) Move 2 units to Tuesday, 6 units to Thursday, and 6 units to Friday.
E) Move 8 units to Thursday, and 4 units to Friday.