Which of the following is NOT one of the four things needed for aggregate planning?
A) a logical overall unit for measuring sales and output
B) a method to determine the relevant costs
C) a mathematical model that will minimize costs over the intermediate planning period
D) an aggregate demand forecast for an intermediate planning period
E) All of these are needed for aggregate planning.
Correct Answer:

Verified
Correct Answer:
Verified