Which of the following is NOT consistent with level scheduling?


A) varying the use of subcontracting
B) finding alternative work for employees during low-demand periods
C) using built-up inventory to meet demand requirements
D) varying production levels and/or workforce to meet demand requirements
E) All of these are inconsistent with the pure level strategy.