An assembly line with 11 tasks is to be balanced. The longest task is 3.2 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 16 minutes. The line will operate for 600 minutes per day.
(a) Determine the minimum and maximum cycle times.
(b) What range of output is theoretically possible for the line?
(c) What is the minimum number of stations needed if the maximum output rate is to be sought?
(d) What cycle time will provide an output rate of 200 units per day?
Correct Answer:

Verified
(a) Minimum cycle time is 3.2 minutes. M...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q111: Which of the following is NOT a
Q112: A work cell is required to make
Q113: Which of the following is NOT a
Q114: Describe how the visual workplace can increase
Q115: The allowance factor that increases normal time
Q117: A work sampling study requires an acceptable
Q118: The work cell improves layouts by reducing
Q119: If a manager conducting a time study
Q120: It is said that job expansion has
Q121: _ layouts deal with low-volume, high-variety production