Multiple Choice
A bread-making factory has the production process shown in the figure below. There are five operations in sequence. The product only needs to go through one of the parallel machines in each case where parallel machines exist. What is the throughput time of this process?
A) 245 min.
B) 515 min.
C) 130 min.
D) 240 min.
E) 300 min.
Correct Answer:

Verified
Correct Answer:
Verified