Multiple Choice
The critical path for the network activities shown below is ________ with duration ________.
A) A-C-E; 20
B) A-D-E; 18
C) B-E; 14
D) A-B-D-E; 26
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified