    The ________ Distribution Is Used by PERT Analysis to Calculate
Solved

The ________ Distribution Is Used by PERT Analysis to Calculate

Question 22

Question 22

Multiple Choice

The ________ distribution is used by PERT analysis to calculate expected activity times and variances.


A) Normal
B) Beta
C) Alpha
D) Gaussian
E) Binomial

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q17: In a PERT network, non-critical activities that

Q18: What are some of the ethical issues

Q19: A network consists of the following list.

Q20: Consider the network presented in the following

Q21: The phases of project management are:<br>A) planning,

Q23: Ill-defined projects are typified by software development

Q24: The critical path for the network activities

Q25: Variation in activities that are not on

Q26: A(n) _ divides a project into more

Q27: The PERT pessimistic time estimate is an

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines