Given the Project Within the Table Below, Calculate the Following

Question 8

Essay

Given the project within the table below, calculate the following:
(a) The critical path
(b) The minimum project duration
(c) The amount of slack for each activity
Given the project within the table below, calculate the following: (a) The critical path (b) The minimum project duration (c) The amount of slack for each activity

Correct Answer:

verifed

Verified

blured image (a) The critical path is BDEFG
(b) Mini...