Multiple Choice
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?
A) 0.02275
B) 0.34458
C) 0.65542
D) 0.97725
E) 18
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Which of the following statements regarding critical
Q3: In project management, crashing an activity must
Q4: Pirmin's Bike Shop is behind on a
Q5: Which of the following statements regarding PERT
Q6: Which of the following statements regarding PERT
Q8: Given the project within the table below,
Q9: Ethical issues that may arise in projects
Q10: Describe agile projects.
Q11: Project management at the Tour de France
Q12: Gantt charts give a timeline for each