A Project Being Analyzed by PERT Has 38 Activities, 16

Question 7

Multiple Choice

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?


A) 0.02275
B) 0.34458
C) 0.65542
D) 0.97725
E) 18

Correct Answer:

verifed

Verified