Multiple Choice
Which of the following statements regarding PERT times is TRUE?
A) The optimistic time estimate is usually the same as the most likely time estimate.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The expected time estimate is calculated as t = (a + 4m + b) /6.
D) The pessimistic time estimate is an estimate of the minimum time an activity will require.
E) The most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:

Verified
Correct Answer:
Verified
Q107: The standard deviation of project duration is
Q108: The beta distribution is used in project
Q109: A project organization:<br>A) is effective for companies
Q110: A network consists of the following list.
Q111: In PERT, project variance is computed by
Q113: _ is the amount of time an
Q114: Which of the following statements concerning CPM
Q115: Which of the following is NOT one
Q116: Given the critical path below, calculate the
Q117: Shortening the project's duration by deleting unnecessary