Given the Critical Path Below, Calculate the Following

Question 116

Essay

Given the critical path below, calculate the following:
(a) The crash cost per unit time savings for each activity.
(b) The maximum total crash time savings and cost.
(c) The maximum total time-savings with a $3000 budget.
Given the critical path below, calculate the following: (a) The crash cost per unit time savings for each activity. (b) The maximum total crash time savings and cost. (c) The maximum total time-savings with a $3000 budget.

Correct Answer:

verifed

Verified

(a) A saves 1 day for $4000/day, B saves...