A Project Manager Is Interested in Crashing a Project with Variable

Question 75

Multiple Choice

A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ?


A) PERT
B) CPM
C) Gantt Chart
D) either PERT or CPM
E) PERT, CPM, or a Gantt chart are fine.