Multiple Choice
Which of these statements regarding time-cost tradeoffs in CPM networks is TRUE?
A) Crashing is possible even if there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration, but noncritical, activities.
C) Activities not on the critical path can never be on the critical path, even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the noncritical tasks.
E) The crash time always exceeds the normal time.
Correct Answer:

Verified
Correct Answer:
Verified
Q58: A project being analyzed by PERT has
Q59: Which of the following projects was NOT
Q60: The network below represents a project being
Q61: Identify several advantages of using PERT (and
Q62: Draw the AOA and AON networks for
Q64: A simple CPM network has three activities,
Q65: Which of the following statements regarding CPM
Q66: Identify, in order, the six steps basic
Q67: Which of the following statements regarding time-cost
Q68: Which of the following statements about Bechtel