Solved

Which of the Following Statements Regarding Time-Cost Tradeoffs in CPM

Question 67

Multiple Choice

Which of the following statements regarding time-cost tradeoffs in CPM networks is FALSE?


A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions