Multiple Choice
Which of the following statements regarding time-cost tradeoffs in CPM networks is FALSE?
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.
Correct Answer:

Verified
Correct Answer:
Verified
Q62: Draw the AOA and AON networks for
Q63: Which of these statements regarding time-cost tradeoffs
Q64: A simple CPM network has three activities,
Q65: Which of the following statements regarding CPM
Q66: Identify, in order, the six steps basic
Q68: Which of the following statements about Bechtel
Q69: Three critical path activities from the same
Q70: A(n) _ is an organization formed to
Q71: Consider the network described in the table
Q72: What is the objective of critical path