Multiple Choice

The decision tree of a project is represented by the following graph: The decision tree of a project is represented by the following graph:   What is the outcome of an alternative A if the expected monetary value of a project is $4.56? A) $2.0 B) $2.5 C) $5.0 D) $8.4 E) $10.3 What is the outcome of an alternative A if the expected monetary value of a project is $4.56?


A) $2.0
B) $2.5
C) $5.0
D) $8.4
E) $10.3