Multiple Choice
The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?
A) There is no economical way to reduce completion time.
B) Crash Activity 3 by 2 days.
C) Crash Activity 7 by 2 days.
D) Crash Activities 3 and 7 by one day each.
E) Crash Activities 2 and 3 by one day each.
Correct Answer:

Verified
Correct Answer:
Verified
Q38: Which of the following statements correctly describes
Q39: What is the crash cost of an
Q40: Identify some similarities and differences between the
Q41: Which of the following project management tools
Q42: At what stage of a project's lifecycle
Q44: As a rule, each project includes a
Q45: The AON diagram shown represents a project.
Q46: A construction company has just started building
Q47: Developing a new electronics product involves two
Q48: What is "crashing"?<br>A)time until a capital asset