The AON Diagram Shown Represents a Project

Question 43

Multiple Choice

The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed? The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?     A) There is no economical way to reduce completion time. B) Crash Activity 3 by 2 days. C) Crash Activity 7 by 2 days. D) Crash Activities 3 and 7 by one day each. E) Crash Activities 2 and 3 by one day each. The AON diagram shown represents a project. Normal and crash times, and the associated costs, are shown for each activity in the accompanying table. If it is worth $5 000 a day to reduce the project duration, which activity or activities should be crashed?     A) There is no economical way to reduce completion time. B) Crash Activity 3 by 2 days. C) Crash Activity 7 by 2 days. D) Crash Activities 3 and 7 by one day each. E) Crash Activities 2 and 3 by one day each.


A) There is no economical way to reduce completion time.
B) Crash Activity 3 by 2 days.
C) Crash Activity 7 by 2 days.
D) Crash Activities 3 and 7 by one day each.
E) Crash Activities 2 and 3 by one day each.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions