True/False
Because direct costs are assumed to be developed from "normal" methods and in a "normal" amount of time, any reduction in activity time should add to the costs of the activity.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q96: When do you know you have crashed
Q97: Costs such as labor, materials, equipment, or
Q98: Reducing project duration<br>A) involves crashing all activities
Q99: What is crashing? Include a discussion of
Q100: Which of the following correctly calculates an
Q102: Consider the following table of activities that
Q103: The direct cost for completing an activity
Q104: Design flaws, equipment breakdown and adverse weather
Q105: One way of reducing project costs is
Q106: Consider the following table of activities that