Reducing Project Duration

Question 98

Multiple Choice

Reducing project duration


A) involves crashing all activities to their crash point.
B) can only be done when resources are not constrained.
C) is always more expensive.
D) tends to increase network sensitivity.
E) should be considered for all projects.