Multiple Choice
When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?
A) The inherent risk associated with the activity
B) How crashing will impact the morale and motivation of the individuals working on that activity
C) Resource availability after crashing that activity
D) The level of difficulty involved in completing the activity
E) When during the project the activity will occur
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Crashing frequently results in over allocation of
Q24: For most projects, the estimation of a
Q25: _ is the rearranging of the project
Q26: It is going to cost $120,000 a
Q27: When crashing an activity, you always crash
Q29: Resources are frequently over-allocated when crashing a
Q30: According to Brooks' Law, adding more people
Q31: The cost slope of an activity is
Q32: Given an equal level of risk and
Q33: Which of the following is NOT considered