Multiple Choice
____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially.
A) Laddering
B) Fast tracking
C) Batching
D) Concurrency
E) Sequencing
Correct Answer:

Verified
Correct Answer:
Verified