Multiple Choice
In order to shorten the duration of a project the project manager should limit the choices of activities to just those that are on the __________.
A) shortest path
B) path with the greatest variability
C) critical path
D) path with the least amount of resources required
E) path with the most resources required
Correct Answer:

Verified
Correct Answer:
Verified