There are fewer options available for reducing project time if you are __________________ than if you can spend more than your original budget.
A) time-constrained
B) vision-limited
C) schedule-constrained
D) resource-constrained
E) physically-constrained
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q84: Making the decision to crash is the
Q85: An activity's crash cost includes _ costs.<br>A)
Q86: In order to shorten the duration of
Q87: A reasonable, quick comparison between options for
Q88: Crashing a more expensive activity may be
Q90: Why is the project duration with the
Q91: The relationship between the normal point and
Q92: If indirect costs are a significant percentage
Q93: The simplest way to reduce cost on
Q94: When reducing project duration, the crash cost